There are several tasks in this process: installing a computer, connecting to the Internet, preparing the workstation, and providing access to corporate systems. Each of these tasks is important, but they do not necessarily depend on each other in a strict order. For example, the computer can be installed at the same time as connecting to the Internet, and preparing the workstation can be completed in parallel with providing access to corporate systems. In this case, a strict sequence of tasks is not required. When tasks depend on each other Now let's imagine another situation. You need to upgrade your corporate IT infrastructure. There are several key stages in this process: purchasing new equipment, setting up network equipment, installing servers, and migrating data.
Here, the order of tasks becomes spain phone number list critical. servers cannot be installed before network equipment is configured, and data cannot be migrated before servers are installed. In this case, each task logically depends on the previous one. Example of dependent tasks with different performers Let's consider another complex process, for example, the development of a new software product. This project involves various specialists: developers, testers, designers and project managers. Each stage of work has its own dependencies: FS (Finish-to-Start): The developer cannot start writing code until the design phase is complete. FF (Finish-to-Finish): Functionality testing cannot be completed until the code is finished. SS (Start-to-Start): Requirements analysis can begin simultaneously with the start of design.
SF (Start-to-Finish): Documentation preparation can start when development begins and end when development ends. Keeping track of all these dependencies in a simple task list or notes can lead to chaos and missed deadlines. How can this be done in a primitive TODO or Excel? Although full-fledged dependency management is best done in specialized tools (e.g. MS Project, Jira), you can try simplified methods in primitive TODO or Excel: 1. Using color codes and labels: Define color codes for different types of dependencies: Red for critical dependencies (FS - Finish-to-Start). Yellow for dependencies that can be executed in parallel (SS - Start-to-Start). Green for dependencies that must complete at the same time (FF - Finish-to-Finish).
New equipment cannot be configured before it is purchased
-
- Posts: 261
- Joined: Tue Jan 07, 2025 4:22 am